 Rehab / CSR changes in the works - Updated 6/24/17

Go down 
Go to page : Previous  1, 2, 3, 4, 5, 6, 7  Next
AuthorMessage
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Fri Feb 24, 2017 7:47 am

You can see the tub/stand up shower, two sinks and the ceiling fan (on the right side of the page) coming to the new rooms


_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Mon Mar 13, 2017 6:36 am

Updated - Rancho 7a is almost complete and then the room renovations will be moving to cabana 8a.

_________________
Visit this link to find answers to some of CSR's FAQ.


Last edited by Buzz2001 on Sat May 27, 2017 7:16 am; edited 1 time in total
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Thu Apr 27, 2017 9:08 am

Apparently cabana 8a will close for renovations on Friday and Rancho 7A will open up that day.

_________________
Visit this link to find answers to some of CSR's FAQ.


Last edited by Buzz2001 on Sat May 27, 2017 7:16 am; edited 1 time in total
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Fri Apr 28, 2017 10:40 pm

New room in rancho 7a

New room video

_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Sat Jun 24, 2017 11:11 pm

Cabana 8a is open!

_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Wed Jul 05, 2017 6:01 pm

Casita 1 is up next!

_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
FAUguy
CSR Newbie
CSR Newbie


Join date : 2017-08-02
Location : South FL
Posts : 7

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Wed Aug 02, 2017 7:08 am

Buzz2001 wrote:
Casita 1 is up next!
I have stayed at CSR many times of the years, as it's our favorite Moderate resort.
A few days ago we booked reservation for Aug 27 (4 nights) Water View (Standard not available).
We usually like to stay in Ranchos 7B Ground Floor, as the room is close to the quite pool and the main pool/dig site.

Now with the new room renovations going on, I see that it is noted in here that Ranchos 7A and Cabanas 8A have been completed, so then Ranchos 7B hasn't been done yet (older room)?
We would like to call to make a request for a renovated room, but if it's just the Ranchos 7A and Cabanas 8A that is done, I'm not sure which would be the better choice...though since it is a "water view room" that would probably mean the Cabanas 8A (since Ranchos 7A is all standard view rooms).

Thank you.
Back to top Go down
View user profile
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Wed Aug 02, 2017 9:49 pm

welcome #2 to the CSR Forum!

Correct, cabana 8a would be the waterview rooms of those two choices.

_________________
Visit this link to find answers to some of CSR's FAQ.


Last edited by Buzz2001 on Mon Sep 18, 2017 6:29 am; edited 1 time in total
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
FAUguy
CSR Newbie
CSR Newbie


Join date : 2017-08-02
Location : South FL
Posts : 7

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Tue Aug 08, 2017 10:45 pm

Buzz2001 wrote:
welcome #2 to the CSR Forum!

Correct, cabana 8a would be the waterview rooms of those two choices.
Ok, I ended up calling and requested a ground-floor room in Cabanas 8A.
Back to top Go down
View user profile
FAUguy
CSR Newbie
CSR Newbie


Join date : 2017-08-02
Location : South FL
Posts : 7

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Sun Sep 17, 2017 12:01 pm

Buzz2001 wrote:

Correct, cabana 8a would be the waterview rooms of those tow choices.
Due to some circumstances, was not able to make it in Aug and had to cancel.
So now I have a new reservation for mid Nov (as Dec FL Res is all booked).
Has there been any further updates as to which buildings are finished on next on the list for renovation?
Back to top Go down
View user profile
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Mon Sep 18, 2017 6:30 am

Not yet but casita 1 and/or 3 may be done by that time.

_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Sat Sep 30, 2017 8:23 am

Casita 1 and 3 update photos.
















_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
FAUguy
CSR Newbie
CSR Newbie


Join date : 2017-08-02
Location : South FL
Posts : 7

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Sun May 27, 2018 1:45 am

Since we had to cancel our plans for last summer at CSR, we are looking to go mid-August 2018 for 4-5 nights. With all the construction going on (can see it in videos by Tim Tracker) it looks like the more quiet area to stay in is still the Ranchos area. Do we know if all the buildings and rooms have been refurbished in Ranchos, or is it still being done?
Back to top Go down
View user profile
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Mon May 28, 2018 8:16 am

Renovations/Construction/Complete

Casita 1, 2, and 3 (preferred) - COMPLETE
Casita 4 and 5 (standard and waterview) - COMPLETE
Rancho 6a (standard and waterview) - under rehab
Rancho 6b (standard) - CLOSED (as of 5/22/18)
Rancho 7a (standard) - COMPLETE
Rancho 7b (standard and quite pool view) - TBD
Cabana 8a (standard and waterview) - COMPLETE
Cabana 8b (standard and waterview) - TBD
Cabana 9a (standard and waterview/quiet pool) - TBD

Tower - Under construction through Summer 2019
Lake Restaurant - Under construction through Summer 2019
Walkways over Lake - Under construction
Pepper Market Rehab - Under way through Fall 2018
Pool Rehab - 9/4/18 through 12/12/2018

_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
FAUguy
CSR Newbie
CSR Newbie


Join date : 2017-08-02
Location : South FL
Posts : 7

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Fri Jun 08, 2018 5:03 am

Buzz2001 wrote:
Renovations/Construction/Complete

Casita 1, 2, and 3 (preferred) - COMPLETE
Casita 4 and 5 (standard and waterview) - COMPLETE
Rancho 6a (standard and waterview) - under rehab
Rancho 6b (standard) - CLOSED (as of 5/22/18)
Rancho 7a (standard) - COMPLETE
Rancho 7b (standard and quite pool view) - TBD
Cabana 8a (standard and waterview) - COMPLETE
Cabana 8b (standard and waterview) - TBD
Cabana 9a (standard and waterview/quiet pool) - TBD

Tower - Under construction through Summer 2019
Lake Restaurant - Under construction through Summer 2019
Walkways over Lake - Under construction
Pepper Market Rehab - Under way through Fall 2018
Pool Rehab - 9/4/18 through 12/12/2018

Going up mid August.
We usually request the Rancho's 7B or 6B since it's close to the quiet pool and Dig Site pool.
But 7B hasn't been done yet (so older room style) and 6B is closed as of 5/22 (does that mean its being refurb next?)
So that only leaves Rancho 7A as done, 6A currently under refurb, and 7A is TBD (still older room).
The Cabanas 8A is complete, but would probably have more noise than Rancho's since it's across the water from the Tower building construction.
Back to top Go down
View user profile
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Fri Jun 08, 2018 6:42 am

Correct, 6a is in process and 6b is underway was well. We stayed in 8a and the amount of noise is minimal.

_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
jazzinator
CSR Newbie
CSR Newbie


Join date : 2012-01-16
Posts : 2

PostSubject: Question re: refurbishments and main pool   Sun Jul 01, 2018 4:12 pm

I know that (almost) nothing is certain in life. But, given that, what is the likelihood of the main pool refurb finishing by roughly 12/12/18? Just curious - I have a Xmas trip pending for 12/21, and it would be awesome if the main pool is available and weather permits.

Also, any idea about what exact changes they are making at the main pool?

Thanks!
Back to top Go down
View user profile
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Tue Jul 03, 2018 6:51 am

I would say chances are good for you to be swimming for your trip

_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
FAUguy
CSR Newbie
CSR Newbie


Join date : 2017-08-02
Location : South FL
Posts : 7

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Sat Aug 11, 2018 5:43 am

Buzz2001 wrote:
Correct, 6a is in process and 6b is underway was well. We stayed in 8a and the amount of noise is minimal.
So this is no good.
Due to some medical tests next week, we had reschedule the trip from next week to mid September.
I thought this would be OK, and even the FL Res room rate was slightly less.
But then I remembered to check on here, and saw the post from before saying the Dig Site pool would be closed for renovation.
If that is the case, then will have to book another hotel, or just cancel all together, as we planned on spending most of the time at the pool.
Back to top Go down
View user profile
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Sat Aug 11, 2018 7:39 am

Yes, pool closes 9/4/18 to 12/12/18

_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
FAUguy
CSR Newbie
CSR Newbie


Join date : 2017-08-02
Location : South FL
Posts : 7

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Sun Aug 12, 2018 7:41 am

Buzz2001 wrote:
Yes, pool closes 9/4/18 to 12/12/18
Ok. Changed room from Sept to last week in Aug. Otherwise wouldn't go again until next April/May.
Back to top Go down
View user profile
UncleMike
CSR Newbie
CSR Newbie
avatar

Join date : 2016-04-02
Posts : 6

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Fri Aug 17, 2018 11:01 am

Hey Buzz....
Do you, or perhaps any one else, know if the A/C override in the refurb rooms is the same as in the old rooms?
I'm a heat sensitive North Stater and using the override on our last trip to CSR was a Godsend.  
Back to top Go down
View user profile
Buzz2001
Nado's #1 Fan!
Nado's #1 Fan!
avatar

Join date : 2009-07-29
Location : Connecticut
Age : 56
Posts : 4752

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Sat Aug 18, 2018 8:00 am

Here is the instructions for all three types of thermostats at CSR

https://buzz2k1.wixsite.com/coronado/ac-override

_________________
Visit this link to find answers to some of CSR's FAQ.
Back to top Go down
View user profile http://buzz2k1.wix.com/coronado
UncleMike
CSR Newbie
CSR Newbie
avatar

Join date : 2016-04-02
Posts : 6

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Sat Aug 18, 2018 10:51 pm

Thanks.... Very Happy
Back to top Go down
View user profile
minnie-mouse
CSR Regular
CSR Regular
avatar

Join date : 2011-12-04
Location : Maryland -too far from WDW!
Posts : 92

PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   Thu Sep 20, 2018 4:49 pm

Hey Buzz, do you know what kind of changes they are doing to the pool area and Siestas?
Back to top Go down
View user profile
Sponsored content




PostSubject: Re: Rehab / CSR changes in the works - Updated 6/24/17   

Back to top Go down
 
Rehab / CSR changes in the works - Updated 6/24/17
Back to top 
Page 6 of 7Go to page : Previous  1, 2, 3, 4, 5, 6, 7  Next
 Similar topics
-
» Rehab / CSR changes in the works - Updated 6/24/17
» More building works in Magaluf?
» California Grill to close for rehab in 2013
» Room rehab
» Pool rehab photos...

Permissions in this forum:You cannot reply to topics in this forum
Coronado Springs Resort Forum :: Comments, Questions & Trip Planning-
Jump to: